The Interface Point: How to Document Fire Alarm and ELV Links So Nothing Gets Built Twice
Every project has a handful of places where the fire alarm has to talk to something else: the lifts, the hold-open doors, the smoke dampers, the PA system, the BMS, the access control. On the drawing set these are the smallest symbols on the sheet and the biggest source of site arguments. The reason is structural, not technical. Two different designers produce the two sides, and neither drawing on its own shows the whole point.
Here is how to document those interfaces so the set is complete, the schedule matches the drawing, and nobody builds the same relay twice.
1. Every interface is one point, with one owner
An interface point is a single electrical meeting place: a relay module in the fire alarm panel feeding a pair of terminals in the lift controller, a set of contacts closing a damper actuator, a volt-free contact releasing a mag lock.
Two rules keep it clean:
- The point appears on both drawings, under the same tag. The fire alarm set shows the module and the outgoing cable. The ELV or services set shows the incoming terminals at the equipment.
- Only one drawing owns the terminal. The side that supplies the module shows the terminals as real geometry and lists the cable. The other side shows the incoming connection and marks it "by others", with the other party actually named. "By others" with nobody named is how a point ends up installed by no one.
If both drawings show a complete circuit, you will get two cables pulled to the same terminal strip. If neither shows it, the point gets discovered during commissioning, when the ceiling is closed.
2. The seven facts every interface point needs
Before a symbol goes on a drawing, each point has to answer these:
- Function. What actually happens when the fire alarm operates. Not "interface to lift", but "recall cars to the designated landing and hold doors open".
- Direction. Fire alarm to the other system, other system to fire alarm, or both ways. A two-way point is two rows in the schedule.
- Signal type. Volt-free contact, supervised input, 24 V DC switching, an audio priority input, a data link. This decides the module and the cable.
- Module at each end. Which module in the panel, which input card in the receiving equipment.
- Cable and route. Type, size, and whether the route is fire-rated. A fire-rated route is a drawing requirement, not a note for the installer to work out.
- Who supplies, installs, terminates and tests. Four separate names. They are often four different companies.
- Fail-safe state. What the receiving system does when the signal arrives and when power is lost. This is the fact most often missing, and the one an installer will otherwise decide for you.
That last one matters more than it looks. A mag lock that stays locked on alarm is a life-safety failure. A damper that stays open spreads smoke. A lift that does not home traps people. None of those outcomes are visible from a symbol; they only exist if the schedule states them.
3. The interface schedule
The schedule is the document that carries all seven facts. One row per point. A full column set is: tag, from, to, function, signal type, module at each end, cable type and route, supplied by, installed by, terminated by, tested by, fail-safe state, and drawing reference.
That is a wide table, and it should be. On real projects the columns that get dropped first are the ones that cause the argument: terminated by, tested by and fail-safe.
Worked example: a six-point interface on a mid-size commercial building
A fire alarm panel with a lift, hold-open doors, smoke dampers, a PA system, a BMS link and access control:
| Tag | From | To | Function | Signal | Cable | Supplied / terminated by | Fail-safe |
|---|---|---|---|---|---|---|---|
| IF-01 | FACP | Lift controller | Recall cars to designated landing, hold doors open | Volt-free N/O contact from relay module | 2C 1.5 mm² fire-rated | FA contractor supplies module, terminates at lift controller terminals | Lift returns to designated landing on signal or on loss of FA power |
| IF-02 | FACP | Door holder circuit | Release 24 V hold-open magnets | Relay module switching 24 V DC | 2C 1.5 mm² fire-rated | FA supplies module; electrical contractor supplies 24 V circuit | Doors close on signal and on power loss |
| IF-03 | FACP | Damper actuators | Close smoke/fire dampers on alarm | Relay module, 24 V | 2C 1.5 mm² fire-rated | FA supplies module; mechanical contractor supplies actuators | Dampers close on signal and on loss of power |
| IF-04 | FACP | PA / voice alarm | Mute background music, route evacuation message | Relay contact plus audio priority input | Audio signal cable | PA contractor supplies priority input; FA supplies contact | PA takes priority for the duration of the alarm |
| IF-05 | FACP | BMS | Report alarm, fault and supervisory status | Data link (gateway) | Data cable | BMS contractor terminates at their controller | BMS is monitoring only; it does not control the fire alarm |
| IF-06 | FACP | Access control | Release all controlled doors on alarm | One relay contact per controller | 2C 1.5 mm² fire-rated | ACS contractor supplies the input; FA supplies the contact | Doors release on signal and on loss of FA power |
Notes on the rows above, because the notes are where the design actually lives:
- IF-01 needs a named landing. "Designated landing" is only a fact once the lift contractor and the fire strategy agree on which floor it is.
- IF-03 is one row per damper zone if the actuators are grouped; one row per actuator if they are individually controlled. Decide which before you count.
- IF-04 has two signals in one row. If the priority input is a separate pair of terminals, split it into IF-04A and IF-04B so each terminal has an owner.
- IF-05 is deliberately one-directional. If the BMS is also allowed to send anything to the fire alarm, that is a second point and it needs its own approval chain.
- IF-06 is usually one contact per access control controller, not one per door. State the count so the BOQ matches.
Six points, one page. That page is what the commissioning agent will ask for, and it is what the installer will build from.
4. Tags that let two drawing sets join
The schedule only works if the tag is the same string everywhere: on the fire alarm drawing, on the ELV drawing, in the schedule, in the panel's cause-and-effect matrix, and on the as-built.
A tagging convention that holds up:
- Prefix by system. IF for fire alarm interfaces, and a system prefix inside the row (IF-LIFT-01, IF-ACS-01) if the project has more than a handful.
- Sequence and never reuse. A deleted point keeps its number retired. If IF-03 becomes IF-07 in revision C, someone is going to commission the wrong terminal.
- Tag as an attributed block, not loose text. A copied device with loose text keeps the old address. An attributed tag travels with the symbol when you copy it, which is the difference between a schedule that matches the drawing and one that drifts by revision B.
- Generate the schedule from the drawing. If the schedule is typed separately, it is a second source of truth, and the two will disagree.
5. Symbols, and why the legend has to declare its basis
Three symbol convention families turn up on the same projects:
- IEC 60617 for graphical symbols on diagrams.
- NFPA 170 for fire safety and emergency symbols.
- TIA-606 for the administration and labelling of telecommunications infrastructure.
They do not use identical geometry, and none of them fixes a symbol for every device you will draw. A dome camera, a long-range card reader, a turnstile and a help point are all common devices with no single published symbol that everyone uses. So the legend has to be honest about where each symbol comes from:
- Pick one family per drawing set and say which one in the legend. Do not mix families on the same sheet.
- Where no published symbol covers the device, mark it as drafting practice. That is not a weakness; it is a fact the reviewer can check.
- Draw interface points the same way every time: a module box with the function written next to it, and a short signal arrow at the system boundary. The arrow points in the direction the signal travels, and a two-way point gets two arrows.
- Give the legend a basis column: symbol, block name, description, layer, and the basis it is drawn on.
That basis column is the review-proof move. When a reviewer asks which convention a symbol follows, the answer is already on the sheet, and you are not defending a drawing from memory in a meeting.
6. The five failures that come back from review
- The point is drawn on neither set. Both sides assumed the other would show it.
- Tag mismatch. The fire alarm drawing says IF-03, the access control drawing says "FA relay 3". Nobody can prove they are the same terminal.
- Cable route claimed twice, or not at all. Two contractors price the same 40 m of tray, or nobody does.
- "By others" with no others named. The note survives to site and dies there.
- No fail-safe state. The installer picks a default, and the default is "stay as it is".
Every one of these is fixed by the same thing: a schedule with named owners, plus a drawing that agrees with it.
The library I use for the ELV side
I design fire alarm and ELV systems for a living, and I drew the ELV half of these interfaces into a block library so the symbols and the schedule stop drifting apart: 68 AutoCAD blocks organised by system, including 7 fire alarm interface blocks (relay module, fire door release, lift homing, PA override, damper, BMS, fire-rated cable route) alongside CCTV, access control, data and network, intercom, PA, intruder, and power and containment.
Each block is defined on its own layer, so a device lands on the right layer even when you insert it while the wrong layer is current. The pack also has a 12-layer template with colours, linetypes and lineweights set, an attributed device tag block with TAG / TYPE / ADDR, a legend and index that carries the basis each symbol is drawn on, an A1 title block with editable attributes, and a device schedule workbook whose library-block column fills itself from the symbol map.
On the standards: the legend marks each symbol as IEC 60617 style, NFPA 170 style, TIA-606 convention, or drafting practice, and no clause or symbol reference number is claimed anywhere. The standards are paywalled, so verify against your own copies before you issue.
It is $29 here: ELV & Fire Alarm Interface Symbol Library for AutoCAD
The full fire alarm device set (detectors, call points, sounders, panel, EOL) is a separate library on the same store, along with my battery sizing, BOQ and earthing calculation tools: firealarmcad.gumroad.com
If your office documents interfaces differently, I would like to compare schedules in the comments, especially the columns you use to prove who terminates what.